Free Commercial Remodel Estimate Templates (2026)

Free Commercial Remodel Estimate Templates (2026)

Quick answer: Commercial remodels cost about $60 to $125 per square foot all in for 2026, and our templates land inside that range. A 5,000 SF office buildout comes to about $317,000 ($63 per SF), a 6,000 SF auto shop update about $454,000 ($76 per SF), and a 3,000 SF restaurant conversion about $370,000 ($123 per SF), with kitchens at the top of the range.

Commercial remodels punish loose estimates. You are pricing work inside someone else’s building, around a tenant or a landlord, with hidden conditions behind every wall and a code official who may require upgrades the moment you pull a permit. A missed demolition line or an unpriced fire alarm change comes straight out of your profit.

These three templates cover jobs that show up constantly: a 5,000 SF office buildout, a 3,000 SF space converted into a restaurant, and a 6,000 SF auto service shop update. Each is broken into the scopes you actually coordinate, from general conditions and demolition through mechanical, electrical, plumbing, and life safety, with quantities, units, and unit costs you can change.

The unit costs are mid-range 2026 figures for a typical U.S. market. Use them for a first draft, then replace them with your own subcontractor bids and supplier quotes.



How to Use These Templates

Each template is organized by scope, with a subtotal for each section and a summary at the bottom. Here is how to make them work for your project:

  1. Walk the space. Document existing conditions, ceiling heights, utilities, access, and anything that will constrain demolition or deliveries.
  2. Confirm the code path. Ask the building department what triggers upgrades, like accessibility, fire alarm, or sprinkler changes.
  3. Update quantities from plans or field measurements. Replace square footage, linear footage, and counts with your own takeoff.
  4. Replace lump sums with bids. Electrical, mechanical, and specialty scopes should come from subcontractors.
  5. Adjust general conditions for the schedule, working hours, and any after-hours work.
  6. Set overhead and profit. The templates use 10% overhead and 10% profit. Change both to match your company and the risk.

The costs shown are mid-range U.S. estimates for 2026. Verify pricing before sending a live bid.



Template 1: Office Buildout

This commercial remodel estimate template covers a 5,000 SF interior office buildout with new partitions, ceilings, flooring, lighting, and mechanical modifications. Adjust quantities and unit costs for your space.

General Conditions

Line ItemQtyUnitUnit CostTotal
Building permit and plan review1lot$3,500.00$3,500.00
Project management and supervision1lot$8,500.00$8,500.00
Temporary protection (floors, walls, elevator)1lot$2,200.00$2,200.00
Dumpster and debris removal1lot$3,500.00$3,500.00
Final cleaning (construction clean)1lot$2,800.00$2,800.00
General Conditions Subtotal$20,500.00

Demolition and Prep

Line ItemQtyUnitUnit CostTotal
Selective interior demolition5,000SF$2.50$12,500.00
Ceiling grid removal (partial)2,000SF$0.85$1,700.00
Flooring removal3,000SF$1.50$4,500.00
Demolition and Prep Subtotal$18,700.00

Framing and Drywall

Line ItemQtyUnitUnit CostTotal
Metal stud framing (3-5/8 in, 25 ga)800lin ft$5.50$4,400.00
Drywall (5/8 in Type X, both sides)6,400SF$3.25$20,800.00
Drywall finishing (Level 4)6,400SF$1.75$11,200.00
Sound insulation (R-11 batts in walls)3,200SF$1.25$4,000.00
Fire-rated assemblies (1-hour walls)200lin ft$12.50$2,500.00
Framing and Drywall Subtotal$42,900.00

Electrical

Line ItemQtyUnitUnit CostTotal
Electrical panel upgrade or sub-panel1each$3,500.00$3,500.00
Office receptacles (duplex, 20A)60each$185.00$11,100.00
Dedicated circuits (server room, kitchen)6each$450.00$2,700.00
Data and low voltage rough-in (Cat6)40each$125.00$5,000.00
Light switches (single pole and 3-way)25each$145.00$3,625.00
Exit signs and emergency lights8each$275.00$2,200.00
Electrical Subtotal$28,125.00

Lighting

Line ItemQtyUnitUnit CostTotal
2x4 LED troffer (recessed)60each$285.00$17,100.00
2x2 LED troffer (recessed)20each$245.00$4,900.00
LED downlight (6 in can)15each$195.00$2,925.00
Pendant or decorative fixture (lobby, conference)4each$450.00$1,800.00
Dimmer switches6each$185.00$1,110.00
Lighting Subtotal$27,835.00

HVAC Modifications

Line ItemQtyUnitUnit CostTotal
VAV box relocation or addition4each$1,800.00$7,200.00
Ductwork modifications200lin ft$18.00$3,600.00
Thermostat (programmable)4each$350.00$1,400.00
Return air grille relocation6each$185.00$1,110.00
Supply diffuser relocation8each$165.00$1,320.00
HVAC Modifications Subtotal$14,630.00

Plumbing

Line ItemQtyUnitUnit CostTotal
Break room sink and faucet1each$850.00$850.00
Dishwasher connection1each$350.00$350.00
Restroom fixture (toilet)4each$750.00$3,000.00
Restroom fixture (lavatory)4each$650.00$2,600.00
Water heater (point-of-use)1each$650.00$650.00
Plumbing Subtotal$7,450.00

Flooring

Line ItemQtyUnitUnit CostTotal
Luxury vinyl plank (office areas)4,000SF$5.50$22,000.00
Carpet tile (private offices)1,500SF$4.75$7,125.00
Porcelain tile (restrooms, break room)500SF$9.50$4,750.00
Rubber base (4 in cove)800lin ft$2.25$1,800.00
Flooring Subtotal$35,675.00

Finishes

Line ItemQtyUnitUnit CostTotal
Interior paint (2 coats, eggshell)6,400SF$0.85$5,440.00
Accent wall treatment200SF$3.50$700.00
Ceiling grid and tile (2x2 or 2x4)5,000SF$4.25$21,250.00
Window blinds (roller shades)15each$225.00$3,375.00
Millwork (reception desk, built-ins)1lot$8,500.00$8,500.00
Finishes Subtotal$39,265.00

Fire and Life Safety

Line ItemQtyUnitUnit CostTotal
Fire sprinkler head relocation15each$285.00$4,275.00
Fire alarm devices (smoke, pull, horn/strobe)12each$325.00$3,900.00
Fire extinguisher and cabinet4each$185.00$740.00
ADA signage (room ID, restroom)15each$85.00$1,275.00
Fire and Life Safety Subtotal$10,190.00

Doors and Hardware

Line ItemQtyUnitUnit CostTotal
Solid core wood door with frame (3070)12each$750.00$9,000.00
Glass door (conference room)2each$1,200.00$2,400.00
Hardware set (lever, hinges, closer)14each$285.00$3,990.00
Card reader and access control2each$850.00$1,700.00
Doors and Hardware Subtotal$17,090.00

Summary

Amount
General Conditions$20,500.00
Demolition and Prep$18,700.00
Framing and Drywall$42,900.00
Electrical$28,125.00
Lighting$27,835.00
HVAC Modifications$14,630.00
Plumbing$7,450.00
Flooring$35,675.00
Finishes$39,265.00
Fire and Life Safety$10,190.00
Doors and Hardware$17,090.00
Direct Cost Subtotal$262,360.00
Overhead (10%)$26,236.00
Profit (10%)$28,859.60
Total Estimate$317,455.60

Tips for This Template

  • Confirm the landlord’s rules before you price. Work hours, elevator use, insurance requirements, and approved vendors all change your general conditions.
  • Price the HVAC modifications from a mechanical sub, not a guess. Moving diffusers and adding zones is where buildouts grow.
  • Check whether the existing electrical panel can handle the new load. Service upgrades are often missed.
  • Include a line for patching and protecting the common areas. Landlords notice scuffs and dust.

Template 2: Restaurant Remodel

This commercial remodel estimate template covers converting a 3,000 SF space into a restaurant with a commercial kitchen, hood and fire suppression, walk-ins, and a finished dining room. Adjust quantities and unit costs for your space.

General Conditions

Line ItemQtyUnitUnit CostTotal
Building permit and plan review (change of use)1lot$5,500.00$5,500.00
Health department plan review1lot$1,200.00$1,200.00
Architectural and MEP engineering1lot$12,000.00$12,000.00
Project management1lot$9,500.00$9,500.00
Temporary barriers and dust control1lot$1,800.00$1,800.00
Construction cleaning (multi-phase)1lot$3,500.00$3,500.00
General Conditions Subtotal$33,500.00

Demolition

Line ItemQtyUnitUnit CostTotal
Interior demolition (existing buildout)3,000SF$3.50$10,500.00
Concrete cutting (floor drains, grease trap)40lin ft$45.00$1,800.00
Existing equipment removal1lot$2,500.00$2,500.00
Demolition Subtotal$14,800.00

Kitchen Exhaust and Ventilation

Line ItemQtyUnitUnit CostTotal
Type I hood (grease), stainless steel16lin ft$850.00$13,600.00
Type II hood (heat and steam)8lin ft$550.00$4,400.00
Exhaust ductwork (welded black iron)40lin ft$65.00$2,600.00
Make-up air unit1each$8,500.00$8,500.00
Ansul fire suppression system1lot$6,500.00$6,500.00
Exhaust fan (roof-mounted upblast)2each$2,800.00$5,600.00
Kitchen Exhaust and Ventilation Subtotal$41,200.00

Plumbing

Line ItemQtyUnitUnit CostTotal
Grease trap or interceptor (interior, 100 GPM)1each$4,500.00$4,500.00
3-compartment sink (with drainboards)1each$2,200.00$2,200.00
Hand sink (wall-mount)3each$650.00$1,950.00
Prep sink1each$850.00$850.00
Floor drain (with trap primer)6each$450.00$2,700.00
Mop sink1each$750.00$750.00
Gas line rough-in (kitchen equipment)6each$385.00$2,310.00
Water heater (commercial, 75 gal)1each$3,800.00$3,800.00
Backflow preventer1each$1,200.00$1,200.00
Plumbing Subtotal$20,260.00

Electrical

Line ItemQtyUnitUnit CostTotal
Electrical service upgrade (200A 3-phase)1lot$8,500.00$8,500.00
Kitchen equipment circuits (dedicated 208V/240V)12each$485.00$5,820.00
Receptacles (kitchen, GFCI)15each$195.00$2,925.00
Dining area receptacles and switches20each$175.00$3,500.00
POS/register circuits and data drops4each$325.00$1,300.00
Electrical Subtotal$22,045.00

Walk-In Cooler and Freezer

Line ItemQtyUnitUnit CostTotal
Walk-in cooler (8x10, insulated panels)1each$9,500.00$9,500.00
Walk-in freezer (8x8, insulated panels)1each$12,500.00$12,500.00
Condensing unit (cooler)1each$3,200.00$3,200.00
Condensing unit (freezer)1each$4,500.00$4,500.00
Refrigeration line set and installation1lot$2,800.00$2,800.00
Walk-In Cooler and Freezer Subtotal$32,500.00

Flooring

Line ItemQtyUnitUnit CostTotal
Commercial kitchen tile (quarry tile, anti-slip)1,200SF$12.50$15,000.00
Kitchen floor slope and mud bed1,200SF$4.50$5,400.00
Dining area flooring (luxury vinyl plank)2,000SF$6.50$13,000.00
Restroom tile (porcelain, anti-slip)200SF$10.50$2,100.00
FRP wall panels (kitchen and dish area)800SF$5.75$4,600.00
Flooring Subtotal$40,100.00

Framing, Drywall, and Ceilings

Line ItemQtyUnitUnit CostTotal
Metal stud framing (demising walls)300lin ft$5.50$1,650.00
Drywall (Type X, kitchen side)2,400SF$3.25$7,800.00
Drywall finishing and paint (dining area)3,000SF$2.50$7,500.00
Dining area ceiling (decorative)2,000SF$6.50$13,000.00
Kitchen ceiling (washable FRP panels)1,200SF$4.75$5,700.00
Framing, Drywall, and Ceilings Subtotal$35,650.00

HVAC

Line ItemQtyUnitUnit CostTotal
Rooftop unit (dining area, 5 ton)1each$8,500.00$8,500.00
Kitchen HVAC (make-up air integrated)1lot$5,500.00$5,500.00
Ductwork and diffusers (dining)1lot$4,500.00$4,500.00
Restroom exhaust fan2each$450.00$900.00
Thermostat (programmable)2each$350.00$700.00
HVAC Subtotal$20,100.00

Fire, Life Safety, and Code

Line ItemQtyUnitUnit CostTotal
Fire sprinkler modifications20each$285.00$5,700.00
Fire alarm (horn/strobe, pull station)8each$325.00$2,600.00
Emergency and exit lighting6each$275.00$1,650.00
ADA-compliant restroom build2each$6,500.00$13,000.00
ADA accessible entrance upgrade1lot$3,500.00$3,500.00
Fire, Life Safety, and Code Subtotal$26,450.00

Dining Area Finishes

Line ItemQtyUnitUnit CostTotal
Booth seating (custom banquette)30lin ft$185.00$5,550.00
Bar top (quartz or butcher block)20lin ft$125.00$2,500.00
Decorative lighting (pendants, sconces)15each$275.00$4,125.00
Exterior signage (illuminated)1each$4,500.00$4,500.00
Storefront entry door (ADA, closer)1each$2,800.00$2,800.00
Dining Area Finishes Subtotal$19,475.00

Summary

Amount
General Conditions$33,500.00
Demolition$14,800.00
Kitchen Exhaust and Ventilation$41,200.00
Plumbing$20,260.00
Electrical$22,045.00
Walk-In Cooler and Freezer$32,500.00
Flooring$40,100.00
Framing, Drywall, and Ceilings$35,650.00
HVAC$20,100.00
Fire, Life Safety, and Code$26,450.00
Dining Area Finishes$19,475.00
Direct Cost Subtotal$306,080.00
Overhead (10%)$30,608.00
Profit (10%)$33,668.80
Total Estimate$370,356.80

Tips for This Template

  • Get the health department and fire marshal requirements in writing before you finalize kitchen exhaust, suppression, and plumbing.
  • Hood, makeup air, and walk-in cooler lead times can drive the schedule. Ask for delivery dates along with price.
  • Grease interceptors, floor drains, and gas lines hide big costs. Verify the existing sizes and routes during the site walk.
  • Be clear about what the owner supplies, like kitchen equipment and furniture, and who sets and connects it.

Template 3: Auto Service Shop Remodel

This commercial remodel estimate template covers updating a 6,000 SF auto service shop with new lift anchorage, slab repairs and polish, lighting, ventilation, and a refreshed customer lobby. Adjust quantities and unit costs for your building.

General Conditions

Line ItemQtyUnitUnit CostTotal
Building permit and plan review1lot$3,800.00$3,800.00
Project management and supervision1lot$9,500.00$9,500.00
Temporary protection and dust barriers1lot$2,400.00$2,400.00
Dumpster and debris removal1lot$3,800.00$3,800.00
Final construction clean6,000SF$0.55$3,300.00
General Conditions Subtotal$22,800.00

Demolition and Slab Work

Line ItemQtyUnitUnit CostTotal
Selective interior demolition (lobby, offices, restroom)1,400SF$3.00$4,200.00
Saw cut and remove slab at lift locations6each$950.00$5,700.00
Remove existing lifts and equipment1lot$3,500.00$3,500.00
Slab patching and crack repair6,000SF$1.25$7,500.00
Concrete polish and sealer in service bays4,600SF$6.25$28,750.00
Demolition and Slab Work Subtotal$49,650.00

Concrete and Lift Anchorage

Line ItemQtyUnitUnit CostTotal
Drilled anchor piers or footings for 2-post lifts6each$1,800.00$10,800.00
New trench drain60lin ft$120.00$7,200.00
Epoxy anchor bolts and grout6each$275.00$1,650.00
Floor drain and oil/water separator connection1lot$12,500.00$12,500.00
Concrete and Lift Anchorage Subtotal$32,150.00

Doors and Openings

Line ItemQtyUnitUnit CostTotal
Overhead sectional door (14 ft, with opener)4each$6,800.00$27,200.00
Storefront entry door and glazing (lobby)1lot$8,200.00$8,200.00
Hollow metal door with hardware3each$1,600.00$4,800.00
Doors and Openings Subtotal$40,200.00

Framing, Drywall, and Finishes

Line ItemQtyUnitUnit CostTotal
Metal stud partitions and drywall (lobby, office, restroom)1,800SF$8.50$15,300.00
FRP wall panels in service bays2,200SF$4.75$10,450.00
Acoustical ceiling (lobby and office)1,400SF$5.50$7,700.00
Luxury vinyl plank and tile (lobby, restroom)1,400SF$9.50$13,300.00
Interior paint and epoxy wall base8,500SF$1.10$9,350.00
Service counter and lobby casework1lot$11,000.00$11,000.00
ADA restroom upgrade1lot$9,500.00$9,500.00
Framing, Drywall, and Finishes Subtotal$76,600.00

Plumbing

Line ItemQtyUnitUnit CostTotal
Restroom fixtures and rough-in1lot$8,500.00$8,500.00
Floor drain package1lot$3,500.00$3,500.00
Mop sink and hose bibbs1lot$1,900.00$1,900.00
Water heater1each$2,800.00$2,800.00
Compressed air piping and drops1lot$9,500.00$9,500.00
Plumbing Subtotal$26,200.00

HVAC and Ventilation

Line ItemQtyUnitUnit CostTotal
Gas unit heaters in service bays3each$4,200.00$12,600.00
Shop exhaust fans and make-up air1lot$14,500.00$14,500.00
Vehicle exhaust extraction hose reels4each$2,600.00$10,400.00
Rooftop or split system for lobby and office1each$9,500.00$9,500.00
Ductwork, controls, and balancing1lot$6,500.00$6,500.00
HVAC and Ventilation Subtotal$53,500.00

Electrical and Lighting

Line ItemQtyUnitUnit CostTotal
Panel upgrade and distribution1lot$18,000.00$18,000.00
LED high bay shop lighting package6,000SF$3.25$19,500.00
Lift circuits and shop receptacles6each$950.00$5,700.00
Lobby and office lighting1,400SF$7.00$9,800.00
Data and low voltage (POS, cameras)1lot$7,500.00$7,500.00
Exit signs and emergency lighting8each$275.00$2,200.00
Electrical and Lighting Subtotal$62,700.00

Fire and Life Safety

Line ItemQtyUnitUnit CostTotal
Fire sprinkler modifications20each$285.00$5,700.00
Fire alarm devices8each$325.00$2,600.00
Fire extinguishers and cabinets6each$185.00$1,110.00
ADA and safety signage1lot$2,200.00$2,200.00
Fire and Life Safety Subtotal$11,610.00

Summary

Amount
General Conditions$22,800.00
Demolition and Slab Work$49,650.00
Concrete and Lift Anchorage$32,150.00
Doors and Openings$40,200.00
Framing, Drywall, and Finishes$76,600.00
Plumbing$26,200.00
HVAC and Ventilation$53,500.00
Electrical and Lighting$62,700.00
Fire and Life Safety$11,610.00
Direct Cost Subtotal$375,410.00
Overhead (10%)$37,541.00
Profit (10%)$41,295.10
Total Estimate$454,246.10

Tips for This Template

  • Lift anchorage and slab work depend on what is under the floor. Confirm slab thickness and reinforcement before you price concrete.
  • Ventilation and exhaust requirements are specific to auto service. Have a mechanical sub review the layout.
  • Plan phasing if the shop must stay open. Working around active bays affects labor, schedule, and safety.
  • Check fire and life safety requirements for the occupancy, including extinguishers, alarms, and egress.

Adjusting These Templates for Your Business

Treat Existing Conditions as a Risk Line

Remodels hide surprises. Add a contingency or an allowance for unforeseen conditions, and state in your exclusions how hidden damage, asbestos, and code-required upgrades will be handled. The goal is to avoid absorbing them silently.

Calculate Your True Labor and Overhead Cost

Use job costing tools to see what your crews and project managers really cost with insurance, payroll taxes, and benefits. The 10% overhead here is a placeholder. If your real overhead is higher, your markup has to be too.

Price Phasing and Working Hours

Night and weekend work, occupied buildings, and phased turnover cost more than a vacant space. Reflect that in labor and general conditions rather than hoping the schedule works out.

Move to Digital Estimates

Tenants and owners want a number fast, and they often compare bids. Projul’s estimating tools let you build a detailed estimate from your own cost lines, send it, and carry the same numbers into the budget when you win. To see how it fits, schedule a demo and ask about the free trial.


How to Estimate a Commercial Remodel Step by Step

Step 1: Walk the Space and Document Conditions

Photograph and measure everything. Note ceiling type and height, existing mechanical and electrical equipment, plumbing locations, structural elements, and access routes. Ask what stays and what goes.

Step 2: Confirm Scope and Code Requirements

Review the plans and talk to the building department about triggers for upgrades. Accessibility, fire protection, and energy code changes can add scope quickly in a remodel.

Step 3: Quantify Demolition and Prep

Demolition is easy to underprice. Count partitions, ceilings, flooring, fixtures, and utilities to be removed, plus dumpsters, hauling, and protection of areas that remain.

Step 4: Collect Subcontractor Bids

Send scopes of work to electrical, mechanical, plumbing, fire protection, and specialty subs. Make sure each bid states what is included, because overlap and gaps between trades are common in remodels.

Step 5: Price General Conditions and Schedule

Include supervision, temporary protection, permits, inspections, cleaning, and any after-hours premiums. Build the schedule first so these costs match the duration.

Step 6: Add Contingency, Overhead, and Profit

Add contingency for existing conditions. Then apply overhead and profit. These templates use 10% overhead and 10% profit, with profit calculated on direct cost plus overhead.

Step 7: Review and Submit

Check the math, scope, and exclusions. Have a second person read the estimate against the plans. Confirm the submission format and deadline.


Bid Day and Subcontractor Coverage

Remodel bids are often due fast, and subcontractors price in a hurry. A few habits keep you protected.

Run a coverage sheet. List every scope and mark who has priced it. Open scopes need a backup number before you submit.

Compare inclusions, not just totals. The low mechanical bid may exclude controls, balancing, or curb work. Read each quote against the plans.

Confirm schedule and access. Subs need to know working hours, phasing, and elevator or loading dock limits before they can price correctly.

Watch the gaps between trades. Patching, firestopping, blocking, and final connections often fall between scopes. Decide who owns each.

Freeze the number early. Lock the final figure with time to spare and run a second check. For deeper guidance, see our guides on bid day management and subcontractor management.


Looking for templates for other trades? These free estimate templates follow the same format with realistic line items and pricing for 2026.

Need a template for a different trade? Check our full list of free estimate templates covering dozens of construction trades.


Common Mistakes That Cost Contractors Money on Commercial Remodels

Underpricing demolition. Tearing out finishes, utilities, and slab sections takes longer than it looks, and haul-off is not free. Count it line by line.

Ignoring code triggers. A permit can bring accessibility, fire alarm, and sprinkler upgrades. Ask early and price what applies.

Skipping existing conditions. Opening a wall can reveal bad framing, old wiring, or hazardous materials. Carry a contingency and state your exclusions.

Forgetting working hour premiums. Night work, phased turnover, and occupied buildings raise labor and supervision costs.

Missing long lead items. Hoods, rooftop units, storefront, and electrical gear can run weeks. A late delivery stretches general conditions.

Not coordinating with the landlord. Insurance, approved vendors, deposits, and building rules can add cost and delay if you learn about them late.


What Every Commercial Remodel Estimate Needs Beyond the Numbers

  • Scope of work. Write a clear scope of work by trade, including what is demolished and what stays.
  • Exclusions. State how hidden conditions, hazardous materials, code upgrades, and owner-furnished items are handled.
  • Allowances and alternates. Label them clearly with amounts and what happens if they change.
  • Schedule and working hours. Show duration, phasing, and any after-hours assumptions.
  • Landlord and tenant requirements. Note insurance, access, and approval steps that affect the work.
  • Payment terms. Spell out deposit, progress billing, retainage, and final payment. Use invoicing software to bill on time.
  • License and insurance. Include your license number and proof of coverage.
  • Validity period. State how long your pricing holds.

Frequently Asked Questions

Check the FAQ section above for answers to common questions about commercial remodel costs, existing conditions, markup, and permits.


Start Sending Better Estimates Today

These templates give you a strong starting point for office buildouts, restaurant conversions, and auto shop updates. Update the quantities from your site walk, replace lump sums with bids, and apply your own overhead and profit.

If you want to build and send estimates faster, Projul’s estimating features keep your cost lines, budgets, and change orders in one place. Schedule a live demo and see how it fits your process. A free trial is available after the demo, and plans can also be purchased online at our pricing page.


DISCLAIMER: We make no warranty of accuracy, timeliness, and completeness of the information presented on this website. Posts are subject to change without notice and cannot be considered financial advice.

Want more construction business tips from Projul in your Google results?

Frequently Asked Questions

How much does a commercial remodel cost per square foot in 2026?
Costs vary widely with the building type and scope. Light office buildouts can land around $60 to $90 per square foot, while restaurant conversions with kitchen exhaust, walk-ins, and plumbing run much higher. The templates in this post work out to about $60 to $125 per square foot all in. Price from your actual scope and local subcontractor bids.
What is the difference between a tenant improvement and a commercial remodel?
A tenant improvement is usually interior work done for a tenant inside leased space, often with the landlord's rules and sometimes an allowance. A commercial remodel is a broader term that can include buildouts, renovations, and updates to an existing building. The estimating approach is similar, but tenant work adds landlord approvals and coordination.
How do I price hidden conditions in a remodel?
You cannot price what you cannot see, so carry a contingency or an allowance and state in your exclusions how unforeseen conditions will be handled. Do a thorough site walk, ask for as-built drawings, and note what you could not verify. Spell out how changes will be billed so you are not absorbing surprises.
What markup should I use on commercial remodels?
Many commercial contractors carry overhead and profit that together land somewhere in the mid teens to low twenties on direct cost, depending on risk and competition. The templates here use 10% overhead and 10% profit as a starting point. Remodels carry more unknowns than new builds, so many contractors set markup higher or carry contingency separately.
Do I need permits for a commercial remodel?
In most jurisdictions, yes. Even interior work typically needs a building permit, and electrical, mechanical, and plumbing work may need separate permits. A permit can also trigger accessibility, fire protection, or energy code upgrades. Ask the building department early and price what applies.
How should I handle work in an occupied building?
Plan for phasing, protection, noise and dust control, and after-hours work, and price each one. Coordinate access and hours with the tenant or building manager before you finalize the schedule. Occupied work usually costs more in labor and supervision than a vacant space.
How long should a commercial remodel estimate stay valid?
Most contractors hold pricing for 30 days, and sometimes less when long lead items like hoods, rooftop units, or electrical gear are a big part of the job. State the validity period on the estimate and note that pricing may change if the start date slips.